拉格斯站在{城市环工程提议中被提及。<ref>{{cite web |archiveurl=https://web.archive.org/web/20110708181035/https://www.commentmgr.com/projects/1169/docs/URnews0105c.pdf |archivedate=8 July 2011 |url=https://www.commentmgr.com/projects/1169/docs/URnews0105c.pdf |title=Urban Ring Phase 2 FACT SHEET |date=January 2009|accessdate=18 March 2012}}</ref>该项目希望在波士顿建造环状[[巴士快速交通系統]](BRT),将现有呈辐状的铁路线连接起来,减少市中心换乘站的换乘压力,该项目于2010年否决。<ref>{{cite web |url=http://eeaonline.eea.state.ma.us/EEA/emepa/mepadocs/2010/012710em/pn/14.pdf |title=Re: Urban Ring Phase 2, EOEEA #12565 |date=January 22, 2010 |last=Mullan |first=Jeffery B. |publisher=Massachusetts Executive Office of Energy and Environmental Affairs |accessdate=2020-02-05 |archive-date=2020-03-23 |archive-url=https://web.archive.org/web/20200323171512/http://eeaonline.eea.state.ma.us/EEA/emepa/mepadocs/2010/012710em/pn/14.pdf |dead-url=no }}</ref><ref>{{cite web |archiveurl=https://web.archive.org/web/20170514232004/http://www.massdot.state.ma.us/theurbanring/downloads/Plan_Profile_Drawings.pdf |archivedate=May 14, 2017 |url=http://www.massdot.state.ma.us/theurbanring/downloads/Plan_Profile_Drawings.pdf |title=The Urban Ring Phase 2: Revised Draft Environmental Impact Report/Statement |publisher=Massachusetts Executive Office of Transportation |date=November 2008}}</ref>
===新增通勤铁路站台===
[[ 马萨诸塞湾交通局 ]] 批准了数个沿着西南走廊的小型改造项目,其中拉格斯站为轨道2新增站台。目前,由于仅1号和3号轨道有站台,大概30%的列车不在此站停靠。1993年开始,马萨诸塞湾交通局开始考虑为车站新增站台。<ref name=study /><ref>{{cite web |url=http://www.mbta.com/uploadedfiles/About_the_T/T_Projects/T_Projects_List/Ruggles_Legis_Brief_20120919.pdf |title=MBTA Ruggles Station Commuter Rail Platform Project: Legislative Briefing September 20, 2012 |date=20 September 2012 |publisher=Massachusetts Bay Transportation Authority |accessdate=16 September 2014 |archive-date=2016-12-20 |archive-url=https://web.archive.org/web/20161220103629/http://www.mbta.com/uploadedfiles/About_the_T/T_Projects/T_Projects_List/Ruggles_Legis_Brief_20120919.pdf |dead-url=no }}</ref>2008年,调查研究显示最好在车站新增一个全尺寸800英尺长的站台。<ref>{{cite web |url=http://www.aestreit.com/FeasibilityStudies/2008_ruggles_station_platform_study.pdf |title=Ruggles Station Platform Study |publisher=MASCO Inc. |author=Jacobs Engineering |date=11 September 2008 |accessdate=2 February 2012 |archive-date=2016-03-04 |archive-url=https://web.archive.org/web/20160304082308/http://www.aestreit.com/FeasibilityStudies/2008_ruggles_station_platform_study.pdf |dead-url=no }}</ref>
2012年,交通局主持听证会,新站台将建在现有站台旁,分成两段,中间由一小节 [[ 人行隧道 ]] 连接。<ref name=mbta>{{cite web |url=http://www.mbta.com/about_the_mbta/t_projects/default.asp?id=25059 |archiveurl=https://web.archive.org/web/20160304205504/http://www.mbta.com/about_the_mbta/t_projects/default.asp?id=25059 |archivedate=4 March 2016 |title=Ruggles Station Platform Project |publisher=Massachusetts Bay Transportation Authority}}</ref>工程预计造价为3千万美元,2014年9月,马萨诸塞湾交通局从运输投资促进经济复苏项目筹集2千万美元。除了新站台外,还将对车站照明及安全设施进行升级,对电梯进行更新,并维护现有站台。<ref>{{cite web |url=http://www.dot.gov/sites/dot.gov/files/docs/TIGER14_Project_FactSheets.pdf |title=TIGER 2014 Awards |publisher=U.S. Department of Transportation |date=September 2014 |accessdate=16 September 2014 |archive-date=2015-03-19 |archive-url=https://web.archive.org/web/20150319081912/http://www.dot.gov/sites/dot.gov/files/docs/TIGER14_Project_FactSheets.pdf |dead-url=no }}</ref>
截至2016年3月,工程整体90%设计完成,预计2016年中旬全部完成设计,2016年底开始建造,并于2018年竣工。<ref name=mbta />2016年12月,马萨诸塞湾交通局财务和管理控制委员会批复160万美元,用于对低侧公交专用道进行重建,更换电梯、增加额外车站入口等项目。<ref name=dec2016>{{cite press release |url=https://www.mbta.com/news/2016-12-19/fmcb-votes-expand-design-ruggles-station-transportation-project |title=FMCB votes to expand design of Ruggles Station Transportation Project |publisher=Massachusetts Bay Transportation Authority |date=December 19, 2016 |access-date=2020-02-05 |archive-date=2020-02-03 |archive-url=https://web.archive.org/web/20200203191332/https://www.mbta.com/news/2016-12-19/fmcb-votes-expand-design-ruggles-station-transportation-project |dead-url=no }}</ref>2017年5月至6月进行竞价招标,6月26日签订1970万美元的施工合约。<ref>{{cite web |url=http://www.mbta.com/uploadedfiles/About_the_T/Board_Meetings/M.%20%20Ruggles%20Station.pdf |title=MBTA Construction Contract No. S31CN02: Ruggles Station Commuter Rail Platform Project |date=June 26, 2017 |publisher=Massachusetts Bay Transportation Authority |accessdate=2020-02-05 |archive-date=2017-08-31 |archive-url=https://web.archive.org/web/20170831084356/http://www.mbta.com/uploadedfiles/About_the_T/Board_Meetings/M.%20%20Ruggles%20Station.pdf |dead-url=no }}</ref>
9,017
次編輯